Click, drag, and use the mousewheel directly on the map to explore the area.
If you would like information about a particular stage in the construction click on the icon in the timeline at the bottom of the screen.
Stage 1: Temporary Transmission line SF-1A relocation and temporary transmission line lift structure installation. Phases 1-4
Stage 2: 230kV switchyard construction. Phases 2-5
Stage 3: Transfer existing S61 230kV transmission lines. Phases 6-17
Stage 4: 115kV switchyard construction. Phases 13-18
Stage 5: Transfer existing S61 115kV transmission lines. Phases 19-25
Stage 6: Demolition of old S61 115kV and 230kV switchyards. Phase 26
Stage 7: Transfer existing S106 Plant 115kV lines. Phases 27-28
Stage 8: Distribution substation. Phases 29-31
Construction Complete