Substation Construction Phasing Demo

How to use this application

Click, drag, and use the mousewheel directly on the map to explore the area.

If you would like information about a particular stage in the construction click on the icon in the timeline at the bottom of the screen.

Enhance View

Legend

Stages of Construction

Stage 1: Temporary Transmission line SF-1A relocation and temporary transmission line lift structure installation. Phases 1-4


Stage 2: 230kV switchyard construction. Phases 2-5


Stage 3: Transfer existing S61 230kV transmission lines. Phases 6-17


Stage 4: 115kV switchyard construction. Phases 13-18


Stage 5: Transfer existing S61 115kV transmission lines. Phases 19-25


Stage 6: Demolition of old S61 115kV and 230kV switchyards. Phase 26


Stage 7: Transfer existing S106 Plant 115kV lines. Phases 27-28


Stage 8: Distribution substation. Phases 29-31

Tortoise Relocation

Clearing & Grubbing

3/29/2018 - 4/28/2018

PHASE 1

Temporary Transmission Lift Structure installation (Staged Outages)

230kVs line – Lift Structure

  • De-energize existing 230kVs line
  • Install new temp. lift structure
  • Transfer existing 230kV line from existing tangent structure to new lift structure
  • Remove existing 230kV line tangent structure
  • Re-energize 230kV line

230kV line – Lift Structure

  • De-energize 230kV line
  • Install new temp. lift structure
  • Relocate existing 230kV line to new lift structure
  • Re-energize 230kV line

115kV Flyover – Lift Structure

  • De-energize 115kV flyover line
  • Install new temp. lift structure
  • Re-locate existing 115kV flyover line to new lift structure
  • Re-energize 115kV flyover line
3/30/2018 - 4/15/2018

Phase 2

  • Clear/grub existing trees
  • Begin 230kV switchyard grading
  • De-energize existing capacitor bank
  • Remove cap bank, reactors, BKR 3539, DISC switch
  • Demo foundations of removed equipment
    (Space is required to construct new CEE & Bank #1 230kV bus)
4/18/2018 - 4/22/2018

Phase 3

  • Construction of 115kV temp. shoe-fly line in progress
4/25/2018 - 5/20/2018

Phase 4

  • De-energize existing 115kV line
  • Install fiber optic cable from new transmission line structure 118R4 on line to level 3 telecom building
  • Remove first spans of 115kV line
  • Complete construction of 115kV shoe-fly and fiber connections
  • 115kV switchyard grading to be completed
5/21/2018 - 2/1/2019

Phase 5

  • Construction of new CEE in progress
  • Construction of new 230kV switchyard in progress
  • Installation of 230kV bank #1 strain bus in progress
  • Install three 115kV 100KVA SSVTs for temp. station power to sub #538 in existing sub #61
  • Extend 13kV distribution feeder and install six 13kV 100KVA distribution transformers for backup station power to sub #538
  • At the end of phase 5 new 230kV switchyard/CEE construction complete and functioning
  • (Existing 230kV line in-service may effect construction activities directly under line)
2/6/2019 - 2/11/2019

Phase 6

  • De-energize existing 230kV line
  • Reroute first span of 230kV line
2/12/2019 - 2/17/2019

Phase 7

  • Construction of new 230kV line and S61 tie #1 line in progress
  • Install temp. fiber cable between substations #61 and #538
  • New 230kV line, 230kV bus #3 & #4, and S61 tie #1 line cut into new 230kV switchyard then energized
2/20/2019 - 3/3/2019

Phase 8

  • New 230kV switchyard capacitor banks #3 & #4 to be energized
3/6/2019 - 3/11/2019

Phase 9

  • De-energize existing 230kV line
  • Reroute first span of existing 230kV line
3/12/2019 - 3/17/2019

Phase 10

  • Construction of new 230kV line and S61 tie #2 line in progress
  • New 230kV line and S61 tie #2 line cut ionto new 230kV switchyard then energized
3/20/2019 - 3/25/2019

Phase 11

  • De-energize existing 230kV line
  • Open sub #61 disconnect switch, de-energize existing bus to line a-frame dead-end tower
  • Remove first two spans of existing 230kV line
  • Reroute existing 230kV Strain bus and a-frame dead-end tower
  • Remove temp. lift structure and SF2-1 tower
  • (Existing 230kV line outage needed)
3/26/2019 - 3/31/2019

Phase 12

  • Construction of new 230kV line in progress
  • New 230kV line cut into 230kV switchyard then energized including 230kV bus #1 & #2

Phase 13

  • Construction of new 115kV switchyard in progress
  • (115kV flyover line is in-service - may effect construction activities directly under line)
4/3/2019 - 4/9/2019

Phase 14

  • De-energize existing 230kV line
  • Reroute of the existing 230kV line
  • Remove temp. lift structure and existing S-61-7 structure
  • Remove existing sub 61 230kV line dead-end structure and PT's
  • Demo existing sub 61 230kV line dead-end structure and PT's foundations
  • (Existing 230kV line crosses over the new 230kV switchyard)
4/10/2019 - 4/15/2019

Phase 15

  • Construction of 230kV line and completion of bank #1 230kV bus in progress
  • Installation of fiber cable tos line structure S-61-4 from sub #538 CEE in progress
  • Installation of transformer bank #1 & #2 in progress
  • Installation of 115kV bank #2 strain bus in progress
  • (230kV line crosses over CAP BANK #2))
4/16/2019 - 4/21/2019

Phase 16

  • New 230kV line cut into new 230kV switchyard then energized
4/24/2019 - 5/5/2019

Phase 17

  • New 230kV switchyard capacitors #1 & #2 to be energized
8/1/2019 - 9/1/2019

Phase 18

  • New 115kV switchyard construction complete and functional testing complete
  • Energize 230/115kV Bank #1
  • Energize 115kV switchyard
  • Energize 230/115kV Bank #2
  • Energize 3 115kV 100kVA SSVTs located in sub #538 and cut into sub #538 station power system
  • Relocate 3 115kV 100kVA SSVTs from temp. location in sub #61 to permanent location in sub #538 and cut into sub #538 station power system
9/4/2019 - 9/9/2019

Phase 19

  • De-energize existing 115kV SF-1A line
  • Remove 3 spans of existing 115kV SF-1A line
  • Construction of 115kV STCX-1 line in progress
  • Fiber cable installation from new sub #538 line terminal to level 3 telecom building in progress
  • (Re-use spans of temp. shoe-fly for plant S106 tie line SST1-1)
9/10/2019 - 9/15/2019

Phase 20

  • New 115kV line cut into new 115kV switchyard, fiber reconnected, and line energized from sub #538
  • Re-use two spans of shoe-fly temp. reroute for S106 tie line SST1-1
9/18/2019 - 9/23/2019

Phase 21

  • Complete installation of 115kV temp. plant S106 tie line SST1-1 (including OPGW), except for tying into existing 115kV SF-2 line
  • Install fiber cable from SST1-1 sub #538 terminal to new CEE and to level 3 telecom building
  • Install fiber cable from new SF-2 sub #538 terminal to new CEE and level 3 telecom building
  • De-energize existing 115kV SF-2 line
  • Install new SST1-1 structure and cut SST1-1 tie line phase and OPGW into existing SF-2 line
  • Complete fiber path from Plant to sub #538 CEE; Install 311L relay at Plant for SST1-1 tie line relay protection
  • Remove existing SF-2 line from structure SST1-1 to sub #61
  • Remove existing SF-2 line from sub #61 to existing structure SF-5
  • Remove SF-2 temp. lift structures
  • Complete installation of SF-2 line into new substation terminal in sub #538
9/24/2019 - 9/29/2019

Phase 22

  • New 115kV SF-2 line and 115kV Plant S106 tie line SST1-1 cut into new 115kV switchyard then energized
10/2/2019 - 10/7/2019

Phase 23

  • De-energize existing 115kV Occidental line
  • Reroute of the existing 115kV (Occidental) line
  • Construction of 115kV Occidental line (including OPGW) into new sub #538 terminal in progress
  • Install fiber cable from new sub #538 terminal in to new CEE and to level 3 telecom building
  • Existing SSC-1 to be removed
10/8/2019 - 10/13/2019

Phase 24

  • New 115kV Occidental line cut into new sub #538 115kV switchyard then energized
10/16/2019 - 10/20/2019

Phase 25

  • De-energized existing 115kV Plant line
  • Remove existing Plant line SF-1 and all transmission structures
10/23/2019 - 11/17/2019

Phase 26

  • De-energize 230kV S61 tie #1 and S61 tie #2 lines
  • De-energize existing sub #61 115kV and 230kV switchyards
  • Demo one span of the S61 tie #1 and S61 tie #2 lines and supporting guy wires.
  • Demo existing sub #61 115kV and 230kV switchyards
11/27/2019 - 12/01/2019

Phase 27

  • 115kV SUM-1 line outage
12/04/2019 - 12/08/2019

Phase 28

  • 115kV SP-1 line outage
12/11/2019 - 12/15/2019

Phase 29

  • 115kV Hanson SW-1 line outage
12/18/2019 - 12/22/2019

Phase 30

  • 115kV Jasper SW-2 line outage
2/5/2020 - 2/9/2020

Phase 31

  • De-energize 115kV Occidental line
  • Cut 115kV Occidental line into new 115/13kV distribution substation #539 115kV switchyard
2/12/2020 - 3/9/2020

Phase 32

  • Re-energize 115kV Occidental line
  • Energize new 115/13kV distribution substation
  • Energize distribution substation #539 115/13kV transformer banks #1 and #2 and 13kV switchyard
  • Transfer 13kV distribution load from plant sub #106 to new 115/13kV distribution sub #539
3/12/2020 - 3/23/2020

Phase 33

  • After distribution load removed from plant substation, de-energize temporary 115kV plant tie line
  • Demo temporary 115kV plant tie line
  • Plant substation #106 ready for demolition

Phase 34

Construction Complete

This is a popup for a security alert. Can contain any information or images regarding this security alert.

EXISTING

PHASES 1-3

  • CONSTRUCTION OF TEMPORARY 230KV (SPS-1A) LIFT STRUCTURE
  • CONSTRUCTION OF TEMPORARY 230KV (SF2-1) LIFT STRUCTURE
  • CONSTRUCTION OF TEMPORARY 115KV (SF-2) FLYOVER STRUCTURE
  • BEGIN CONSTRUCTION OF THE 115KV (STCX-1) “SHOE-FLY” AROUND NEW 115KV YARD

PHASES 4-6

  • FINISH CONSTRUCTION OF 115KV (STCX-1) “SHOE-FLY” AROUND NEW 115KV YARD

PHASES 7-9

  • CONSTRUCTION OF NEW 230KV LINE (SPP-1) AND TEMPORARY TIE LINE #1

PHASES 10-12

  • CONSTRUCTION OF NEW 230KV LINE (SX-1) AND TEMPORARY TIE LINE #2

PHASES 12-14

  • CONSTRUCTION OF NEW 230KV LINE (SF2-1)
  • DECOMMISSIONING AND REMOVAL OF EXISTING SF2-1 LINE

PHASES 15-18

  • CONSTRUCTION OF 230KV PEAKER LINE (SPS-1A) AND COMPLETION OF BANK #1 230KVBUS (230KV PEAKER LINE CROSSES OVER CAP BANK #2)

PHASES 19-20

  • CUT 115KV LINE INTO NEW 115KV SWITCHYARD (STCX-1)
  • THREE (3) STRUCTURES (& CORRESPONDING WIRES) TO REMAIN FROM 115KV (STCX-1) “SHOE-FLY” FOR FUTURE USE

PHASES 21-22

  • DE-ENERGIZE EXISTING 115KV PLANT LINE (SF-2)
  • CONSTRUCT TEMPORARY 115KV PLANT TIE LINE (SST1-1)
  • NEW 115KV LINE CUT INTO NEW 115KV SWITCHYARD (SF-2)

PHASES 23-24

  • DE-ENERGIZE EXISTING 115KV OCCIDENTAL LINE (SCC-1)
  • REMOVE FIRST SPANS OF EXISTING 115KV OCCIDENTAL LINE
  • CUT NEW 115KV OCCIDENTAL LINE INTO NEW 115KV SWITCHYARD

PHASE 25

  • DE-ENERGIZE EXISTING 115KV PLANT LINE (SF-1)
  • REMOVE EXISTING 115KV PLANT LINE (SF-1)

PHASE 26

  • DE-ENERGIZE THE 230KV TEMPORARY TIE LINES #1 AND #2, AND REMOVE THE FIRST SPANS CONNECTING TO THE EXISTING SWITCHYARD
  • STRUCTURES LEADING NW FROM THE NEW 230KV SWITCHYARD TO REMAIN UNTIL THE FIRST DEADEND ALONG TEMPORARY TIE LINES #1 AND #2 FOR LIGHTNING PROTECTION

PHASES 27-28

  • DE-ENERGIZE EXISTING 115KV LINE, COMPLETE CUT OVER TO NEW 115KV LINE (SUM-1),NEW 115KV SWITCHYARD
  • DE-ENERGIZE EXISTING 115KV LINE, COMPLETE CUT OVER TO NEW 115KV LINE (SP-1), AND ENERGIZE FROM NEW 115KV SWITCHYARD
  • DE-ENERGIZE EXISTING 115KV LINE, COMPLETE CUT OVER TO NEW 115KV LINE (SW-1), AND ENERGIZE FROM NEW 115KV SWITCHYARD
  • DE-ENERGIZE EXISTING 115KV LINE, COMPLETE CUT OVER TO LINE (SW-2), AND ENERGIZE FROM NEW 115KV SWITCHYARD

PHASES 29-30

  • DE-ENERGIZE 115KV OCCIDENTAL LINE
  • CUT 115KV OCCIDENTAL LINE INTO NEW 115/13KV DISTRIBUTION SWITCHYARD
  • RE-ENERGIZE 115KV OCCIDENTAL LINE

PHASE 31

  • AFTER DISTRIBUTION LOAD REMOVED FROM PLANT SUBSTATION, DE-ENERGIZE TEMPORARY 115KV PLANT TIE LINE (SST1-1)
  • DEMO TEMPORARY 115KV PLANT TIE LINE (SST1-1)
  • PLANT SUBSTATION READY FOR DEMOLITION

FINAL